Gantt Box Chart Tutorial & Template – Download and Try today

Share

Facebook
Twitter
LinkedIn

Gantt Box Chart - An Excel Template & Download

On Firday, we proposed a new chart for showing project plans. I chose an ugly name for it and called it Gantt Box Chart.

Essentially, a gantt box chart is what you get when a gantt chart and box plot go to a bar, get drunk and decide to make out. It shows the project plan like any other gantt chart, and it shows the distribution of activity end dates, like any other box plot.

You can see an example gantt box chart for a fictional software project above.

Today, we will learn how to create a similar chart in Excel. Get a steaming cup of coffee or whatever keeps you going and follow these simple steps to make a gantt box chart.

[Read this post if you want to know what GBC is and how to read it]

1. Set up your data:

Just like any other chart in excel, a gantt box chart too requires well structured data. In our case, we need 5 things.

  1. Activity name
  2. Start Date
  3. Best Case End Date
  4. Realistic (or Plan) End Date
  5. Worst Case End Date

Getting all the 3 variations of End dates can be tricky. But if you are managing projects for long, you might already know how to get these dates. Otherwise, here is one approach, proposed by Joel Spolsky, called as Evidence Based Scheduling that can help you.

We will also need 3 additional helper columns where we need to calculate some numbers so that our gantt box chart can be constructed without resorting to magic wands. These are,

  1. BC: Number of days between Start Date and Best Case End Date
  2. R: Number of days between Best Case End Date and Realistic Date
  3. W: Number of days between Realistic Date and Worst Case End Date

Gantt Box Chart - Source Data

2. Create a Stacked Bar Chart

Add a new stacked bar chart. The series to be stacked are,

  1. Best case end date
  2. R
  3. W

Use the “Activity Name” column for category axis labels.

Now, our chart should look like:

Gantt Box Chart - Stacked Bar Chart

3. Say your favorite curse word and Reverse the categories

Reverse Cateogry Axis Values - Excel Gantt Box ChartOk, time for a minor annoyance. Excel has magically showed the first activity of project at bottom. So, we need to reverse the category axis values before any further.

Just select the category axis, go to format axis (press CTRL+1) and click the little box that says “order reverse in Categories”.

Now, the chart should look like this:

Excel Gantt Box Chart - After reversing category axis values

4. Add Error Bars to Best Case Series

Now, add error bars to the best case series of the chart so that it looks like a line is drawn connecting best case date to start date of each activity. To do that, follow these steps:

  1. Select “best case end date” series.
  2. Add Error Bars (from format ribbon)
  3. Specify the type of error bar as “Negative only”
  4. Select “Custom” for error bar values
  5. Now, point the error bar values to the helper column “BC”
  6. Format the error bar in such a way that no cap is shown and it is thick.

At this point, our gantt box chart should look like this:

Adding Error Bars to Gantt Box Chart

5. Finally, format the chart

Now, our gantt box chart is almost ready. But it is still ugly. We need not hire a Hollywood grade make-up man to beautify this. We just need a few clicks.

  1. Remove legend
  2. Add vertical and horizontal grid lines. Make them subtle.
  3. Change text colors to soothing ones.
  4. Remove fills from all series in stacked bar chart.
  5. Apply borders to 2nd and 3rd series to create a box effect.
  6. Format the date axis,
    1. Adjust the starting point (unfortunately you have to enter the number equivalent of date, like 1-May-2010 as 40299)
    2. Adjust major unit – I used 14 days, you can try something else depending on overall project length.
    3. Set the axis number formatting to d-mmm or mmm or myy or something else that works for you.
  7. Add a chart title

That is all. Our Gantt Box Chart is finally ready. Now, go figure why your project is not on track and do something about it.

Final Gantt Box Chart

Displaying Completed Activities:

The easiest way to show completed activities is to change all 3 end dates to the same date: that of the actual end date. This way, you just see a line when an activity is done and a box when there are variations in end dates.

Of course, you can use another helper column to show a vertical line or a symbol of your choice to denote the end point as well. I leave it to you to figure out that portion.

Download the Gantt Box Chart Template:

I have prepared an excel template for creating Gantt Box Charts quickly. Go ahead and download the version that you want.

Excel 2007+ version | Excel 2003 version

Here is a mirror with both files as a zip. Go on, be awesome 🙂

Share your experiences of using Gantt Box Chart:

If you like this chart and implementing it in one of your projects, do tell me how it went. Or just share your thoughts on this implementation and any suggestions. Go ahead and share.

Templates & Tutorials on Project Management:

Project Management Template Set – Get a copy today

I have made a set of 24 templates that take care of various activities in a project right from planning to time sheets to issues to project status reporting thru dashboards. These templates have been bought by more than 500 project managers all over the world and they are saving hours of time every week using these templates.

Project Management Templates for Excel

Go ahead and a get a copy of my project management templates.

Facebook
Twitter
LinkedIn

Share this tip with your colleagues

Excel and Power BI tips - Chandoo.org Newsletter

Get FREE Excel + Power BI Tips

Simple, fun and useful emails, once per week.

Learn & be awesome.

Welcome to Chandoo.org

Thank you so much for visiting. My aim is to make you awesome in Excel & Power BI. I do this by sharing videos, tips, examples and downloads on this website. There are more than 1,000 pages with all things Excel, Power BI, Dashboards & VBA here. Go ahead and spend few minutes to be AWESOME.

Read my storyFREE Excel tips book

Overall I learned a lot and I thought you did a great job of explaining how to do things. This will definitely elevate my reporting in the future.
Rebekah S
Reporting Analyst
Excel formula list - 100+ examples and howto guide for you

From simple to complex, there is a formula for every occasion. Check out the list now.

Calendars, invoices, trackers and much more. All free, fun and fantastic.

Advanced Pivot Table tricks

Power Query, Data model, DAX, Filters, Slicers, Conditional formats and beautiful charts. It's all here.

Still on fence about Power BI? In this getting started guide, learn what is Power BI, how to get it and how to create your first report from scratch.

8 Responses to “Create a Combination Chart, Add Secondary Axis in Excel [15 Second Tutorial]”

  1. [...] Select the “daily completed” column and add it to the burn down chart. Once added, change the chart type for this series to bar chart (read how you can combine 2 different chart types in one) [...]

  2. [...] set the height series to be plotted on secondary axis. Learn more about combining 2 chart types and adding secondary axis in [...]

  3. [...] To show the years, I have used another dummy series and plotted it on secondary axis (related: how to add secondary axis?) [...]

  4. Thanks for this one!

  5. [...] Choisissez la colonne « Daily Completed » et ajoutez-la au graphique. Une fois ajoutée, changez le type de graphique pour cette série à histogramme (lisez comment combiner 2 types de graphiques en un : combine 2 different chart types in one) [...]

  6. Nat says:

    How do i create a chart that has negative numbers on axis x and y and plot them correctly? I cannot seem to understand how to do this, please help.
    Thanks.

    Nat

  7. MSWebReviewer says:

    You can also plot 2 or more Y axes in Excel using EZplot or Multy_Y from Office Expander.com
    There is a demo version to try.
    Cheers.

Leave a Reply