
On Firday, we proposed a new chart for showing project plans. I chose an ugly name for it and called it Gantt Box Chart.
Essentially, a gantt box chart is what you get when a gantt chart and box plot go to a bar, get drunk and decide to make out. It shows the project plan like any other gantt chart, and it shows the distribution of activity end dates, like any other box plot.
You can see an example gantt box chart for a fictional software project above.
Today, we will learn how to create a similar chart in Excel. Get a steaming cup of coffee or whatever keeps you going and follow these simple steps to make a gantt box chart.
[Read this post if you want to know what GBC is and how to read it]
1. Set up your data:
Just like any other chart in excel, a gantt box chart too requires well structured data. In our case, we need 5 things.
- Activity name
- Start Date
- Best Case End Date
- Realistic (or Plan) End Date
- Worst Case End Date
Getting all the 3 variations of End dates can be tricky. But if you are managing projects for long, you might already know how to get these dates. Otherwise, here is one approach, proposed by Joel Spolsky, called as Evidence Based Scheduling that can help you.
We will also need 3 additional helper columns where we need to calculate some numbers so that our gantt box chart can be constructed without resorting to magic wands. These are,
- BC: Number of days between Start Date and Best Case End Date
- R: Number of days between Best Case End Date and Realistic Date
- W: Number of days between Realistic Date and Worst Case End Date

2. Create a Stacked Bar Chart
Add a new stacked bar chart. The series to be stacked are,
- Best case end date
- R
- W
Use the “Activity Name” column for category axis labels.
Now, our chart should look like:

3. Say your favorite curse word and Reverse the categories
Ok, time for a minor annoyance. Excel has magically showed the first activity of project at bottom. So, we need to reverse the category axis values before any further.
Just select the category axis, go to format axis (press CTRL+1) and click the little box that says “order reverse in Categories”.
Now, the chart should look like this:

4. Add Error Bars to Best Case Series
Now, add error bars to the best case series of the chart so that it looks like a line is drawn connecting best case date to start date of each activity. To do that, follow these steps:
- Select “best case end date” series.
- Add Error Bars (from format ribbon)
- Specify the type of error bar as “Negative only”
- Select “Custom” for error bar values
- Now, point the error bar values to the helper column “BC”
- Format the error bar in such a way that no cap is shown and it is thick.
At this point, our gantt box chart should look like this:

5. Finally, format the chart
Now, our gantt box chart is almost ready. But it is still ugly. We need not hire a Hollywood grade make-up man to beautify this. We just need a few clicks.
- Remove legend
- Add vertical and horizontal grid lines. Make them subtle.
- Change text colors to soothing ones.
- Remove fills from all series in stacked bar chart.
- Apply borders to 2nd and 3rd series to create a box effect.
- Format the date axis,
- Adjust the starting point (unfortunately you have to enter the number equivalent of date, like 1-May-2010 as 40299)
- Adjust major unit – I used 14 days, you can try something else depending on overall project length.
- Set the axis number formatting to d-mmm or mmm or myy or something else that works for you.
- Add a chart title
That is all. Our Gantt Box Chart is finally ready. Now, go figure why your project is not on track and do something about it.

Displaying Completed Activities:
The easiest way to show completed activities is to change all 3 end dates to the same date: that of the actual end date. This way, you just see a line when an activity is done and a box when there are variations in end dates.
Of course, you can use another helper column to show a vertical line or a symbol of your choice to denote the end point as well. I leave it to you to figure out that portion.
Download the Gantt Box Chart Template:
I have prepared an excel template for creating Gantt Box Charts quickly. Go ahead and download the version that you want.
Excel 2007+ version | Excel 2003 version
Here is a mirror with both files as a zip. Go on, be awesome 🙂
Share your experiences of using Gantt Box Chart:
If you like this chart and implementing it in one of your projects, do tell me how it went. Or just share your thoughts on this implementation and any suggestions. Go ahead and share.
Templates & Tutorials on Project Management:
- Excel Gantt Chart Template
- Project Milestones – Timeline Template
- Project Status Dashboard Template
- More resources on using Excel for Project Management
Project Management Template Set – Get a copy today
I have made a set of 24 templates that take care of various activities in a project right from planning to time sheets to issues to project status reporting thru dashboards. These templates have been bought by more than 500 project managers all over the world and they are saving hours of time every week using these templates.
Go ahead and a get a copy of my project management templates.













27 Responses to “Sum of Values Between 2 Dates [Excel Formulas]”
I would apply a filter and use function subtotal, with option 9. This way you can see multiple views based on the filter.
hey Chandoo, the solutions you proposed are very efficient, but if I wanted to be fancy I would do it this way .. the references are as your example workbook.
=SUM(INDIRECT("C"&(MATCH(F5,B5:B95)+4)):INDIRECT("C"&(MATCH(F6,B5:B95)+4)))
I like things simple:
=SUMIF(B5:B95,">="&F5,C5:C95)-SUMIF(B5:B95,">"&F6,C5:C95)
use something like: =SUM(OFFSET(B1,0,0,DATEDIF(A1,D1,"d")))
and have D1 be the date that I want to sum to.
In Excel 2003 (and earlier) I'd use an array formula to calculate either with nested if statements (as shown here) or with AND.
{=SUM(IF(B5:B95>F5,IF(B5:B95<F6,C5:C95,0),0))}
Note that I truly made this for BETWEEN the dates, not including the dates
I turned the data set into a table named Dailies.
I named the two limits StartDate and EndDate.
And used an array formula:
{=SUM((Dailies[Date]>=StartDate)*(Dailies[Date]<=EndDate)*Dailies[Sales])}
If I would still be using the old Excel I would do it as follows:
SUMIF($B$5:$B$95,"<="&H6,$C$5:$C$95)-SUMIF($B$5:$B$95,"<"&H5,$C$5:$C$95)
Works as simple as it is.
Regards
=sum(index(c:c,match(startdate,c:c,1)+1):index(c:c,match(enddate,c:c,1))
=sum(index(c:c,match(startdate,b:b,1)+1):index(c:c,match(enddate,b:b,1))
Great examples and thanks to Chandoo. You have simplified my work.
Hi! great tips I have found in your page, have you seen this
http://runakay.blogspot.com/2011/10/searching-in-multiple-excel-tabs.html
[...] I'm not sure I understand your question fully, but have a look at this: Sum of Values Between 2 Dates [Excel Formulas] | Chandoo.org - Learn Microsoft Excel Online [...]
Thank you! Thank you! Thank you!
=SUMIF(A2:A11;">="&B13;B2:B11)-SUMIF(A2:A11;"<"&A11;B2:B11)
awesome... thank yoo Chandoo!
which is most efficient and fast, if all are efficient ?
Thank you for this formula, I've just spent ages trying to find something to work on my data, I knew it would be possible! Don't care if others think there are easier/other ways to do it, you explained it so I understood it and could apply it to what I was doing so I'm happy!
The above said example is awesome for calculating values between dates,
can you pls let know how to calculate sale values if we have 10 sales boys for
ex: 1,rama
2,krishna
3,ashwin
4,naga
5,suresh
how much rama sale value between 1/jan/2015 to 10/jun/15
how much krishna sale value between 10/jan/2015 to 15/july/2015
i think you understood can you pls let me know the formula for how to calculate the sale between diffrent sale man sale value from master data file
Thanks,
Nagaraju
Hi
I have a list of people's names in column A, I have a list of dates in column B which records the dates they have been off sick, in column C I have either 1 if it is a full sick day or 0.5 if it is a half day.
What I would like to do is to add up the number of dates a specific person has been off within two dates.
For example, I want to look at my list of names and to find Joe Bloggs (column A), then add up all his sick days (column C). The start date will be in cell E1 and the end date will be in F1.
If this possible using SUMIFS?
List of names are in range A2:A100
List of dates in B2:B100
List of sick days (either 0.5 or 1 in C2:C100
The start date is in cell E2
The end date is in cell F2
Your help would be greatly appreciated.
Yes, with the help of SUMIFS you can have the solution.
Note: you need have an extra col. D2 where you will input Name of the person.
=SUMIFS(C2:C100,A2:A100,D2,C2:C100,">="&E2,C2:C100,"<"&F2)
Col. A Col. B Col. C Col.D Col. E Col. F
Name Date Sales
ABC 28-Jun-11 1 MNO 28-Jun-11 25-Sep-11
XYZ 29-Jun-11 0.5
MNO 30-Jun-11 1
PQR 1-Jul-11 1
Typo ERROR / Correction in formula:
Yes, with the help of SUMIFS you can have the solution.
Note: you need have an extra col. D2 where you will input Name of the person.
=SUMIFS(C2:C100,A2:A100,D2,B2:B100,">="&E2,B2:B100,"<"&F2)
Hi
I have a list of people's names in column A, I have a list of dates in column B which records the dates they have been off sick, in column C I have either 1 if it is a full sick day or 0.5 if it is a half day.
What I would like to do is to add up the number of dates a specific person has been off within two dates.
For example, I want to look at my list of names and to find Joe Bloggs (column A), then add up all his sick days (column C). The start date will be in cell E1 and the end date will be in F1.
If this possible using SUMIFS?
List of names are in range A2:A100
List of dates in B2:B100
List of sick days (either 0.5 or 1 in C2:C100
The start date is in cell E2
The end date is in cell F2
Your help would be greatly appreciated.
Viv
@Viv
Can you please post the question in the Chandoo.org Forums
http://forum.chandoo.org/
Please attach a file so that a specific answer can be delivered.
Thanks for this - it solved the problem that I was having. However can someone please explain to me why the "" needs to be around >= and <= as well as why we need to add & in order for the formula to work? Thanks in advance!
This formula works perfectly as well. Any ideas?: =SUM(INDEX(C5:C95,MATCH(H5,B5:B95,1)):INDEX(C5:C95,MATCH(H6,B5:B95,1)))
ikkeman had posted the same thing.
I am trying to sum total a range of cells between date ranges ie column n has $ amounts column d has the transaction dates ie 1/3/2015 or 25/3/2015 or 25/4/2015 column b has the text saying drp or distribution - reinv
In another cell I am trying to sum or total (in column n) with the value of a range of different dates (column d) that contain different text (column b) ie cell n48 is 50, n65 is 85, n165 is 36
with the dates ie cell d48 is 1/3/2015, d65 is 25/3/2015 and d165 is 25/4/2015
with different text that says drp or distribution - reinv ie cell b48 is drp, b65 is distribution - reinv, b165 is drp
If I wanted to sum the amounts between 1/3/2015 to 31/3/2015 with drp then the total would be 50. Also if I wanted to sum the amounts between 1/4/2015 to 30/4/2015 with drp the sum total would be 36 If I wanted to sum the amounts between 1/3/2015 to 31/3/2015 with drp and distribution - reinv the sum would be 115
What would the formula be for these different questions
hope you can help, it has been driving me nuts and cant work it out