Gantt Charts – Project Management Using Excel [Part 1 of 6]

Share

Facebook
Twitter
LinkedIn

Starting this week we are starting a new series of posts on project management using Microsoft excel. I have been working in various projects in the last 6 years and almost in all cases we have been using excel to manage, measure and track various aspects of project. These posts represent few of the things related to project management using excel that I have learned over the years.

Part 1: Preparing & tracking a project plan using Gantt Charts
Team To Do Lists – Project Tracking Tools
Project Status Reporting – Create a Timeline to display milestones
Time sheets and Resource management
Issue Trackers & Risk Management
Project Status Reporting – Dashboard
Bonus Post: Using Burn Down Charts to Understand Project Progress

Excel, because of its grid nature provides a great way to prepare and manage project plans. In this part of the project management using Microsoft excel series we will learn how to prepare and track a project plan using gantt chart in excel.

Preparing a project plan

Not all project plans are same. But most of the project plans have a list of,

  • All activities / phases of project
  • Planned start date of the activity
  • Planned duration of the activity

From tracking perspective, we can add the following,

  • Actual start date of the activity
  • Actual duration of the activity
  • % of the activity completed as of date

As you can see, excel provides a great way to manage such plan. Look at an example project plan made in excel.
Gantt Chart - Excel - Project Plan

But the above plan is more or less static. Using Excel’s features we can make a dynamic gantt chart that can,

  • Update the Gantt chart when dates change
  • Display a separate bar that will grow based on the % completion of each activity
  • Highlight current week / day in a subtle way

In essence, we will create something like this:

Steps for preparing an Gantt Chart

  1. First make the above layout in a new excel sheet
  2. Then we will add several columns in the end, one for each day (or week or month) of the project
  3. We will also designate 3 cells say $N$5, $Y$5, $AL$5 where we will maintain the following values,
    1. In cell $N$5, a selection option that will change the plan between “planned” and “actual” dates
    2. In cell $Y$5, a symbol that we can use to display finished portion of work
    3. In cell $AL$5, where we can enter the current week (or day or month)
  4. Now we will do some conditional formatting (ahem!) that will highlight a particular cell in the grid,
    1. If $N$5 has “Planned” and cell is between planned date and planned date + planned duration
    2. Else, cell is between actual date and actual date + actual duration
  5. We will also write formulas in all the cells (same formula pasted over the entire range) which displays a symbol like solid rectangle. For finding out if we should fill in the symbol or not, we use the % completed column of the gantt chart. Figuring out this formula is part of your home work. 😉
  6. Finally we will adjust formatting like column widths, fonts, colors etc. and freeze top row so that it is easy to scroll and still know what you are looking at.

Once you prepare such plan it is easy to track, find out the status of individual activities and take necessary corrective actions as needed.

Download Excel Gantt Chart Template and Make your own project plan

Feel free to download gantt chart project plan template and make your own project plans using Microsoft Excel.

Download 7 Gantt Chart Templates and 17 other Project Management Templates for Excel – Click here

What next?

In the next part of this series we will understand how to manage day to day activities of projects using to do lists in excel.

Resources for Project Managers

Check out my Project Management using Excel page for more resources and helpful information on project management.

Also check out below pages:

Your Thoughts and Suggestions

Do you work a lot on project management activities? Do you find this content useful? share your feedback and experiences through comments.

Project Management Templates for Excel

Facebook
Twitter
LinkedIn

Share this tip with your colleagues

Excel and Power BI tips - Chandoo.org Newsletter

Get FREE Excel + Power BI Tips

Simple, fun and useful emails, once per week.

Learn & be awesome.

Welcome to Chandoo.org

Thank you so much for visiting. My aim is to make you awesome in Excel & Power BI. I do this by sharing videos, tips, examples and downloads on this website. There are more than 1,000 pages with all things Excel, Power BI, Dashboards & VBA here. Go ahead and spend few minutes to be AWESOME.

Read my storyFREE Excel tips book

Overall I learned a lot and I thought you did a great job of explaining how to do things. This will definitely elevate my reporting in the future.
Rebekah S
Reporting Analyst
Excel formula list - 100+ examples and howto guide for you

From simple to complex, there is a formula for every occasion. Check out the list now.

Calendars, invoices, trackers and much more. All free, fun and fantastic.

Advanced Pivot Table tricks

Power Query, Data model, DAX, Filters, Slicers, Conditional formats and beautiful charts. It's all here.

Still on fence about Power BI? In this getting started guide, learn what is Power BI, how to get it and how to create your first report from scratch.

12 Responses to “29 Excel Formula Tips for all Occasions [and proof that PHD readers truly rock]”

  1. Peder Schmedling says:

    Some great contributions here.
    Gotta love the Friday 13th formula 😀

  2. Aires says:

    Great tips from you all! Thanks a lot for sharing! bsamson, particularly you helped me on a terribly annoying task. 🙂

    (BTW, Chandoo, it's not exactly "Find if a range is normally distributed" what my suggestion does. It checks if two proportions are statistically different. I probably gave you a bad explanation on twitter, but it'd be probably better if you fix it here... 🙂 )

  3. John Franco says:

    Great compilation Chandoo

    For the "Clean your text before you lookup"
    =VLOOKUP(CLEAN(TRIM(E20)),F5:G18,2,0)

    I would like to share a method to convert a number-stored-as-text before you lookup:

    =VLOOKUP(E20+0,F5:G18,2,0)

  4. Chandoo says:

    @Peder, yeah, I loved that formula
    @Aires: Sorry, I misunderstood your formula. Corrected the heading now.
    @John.. that is a cool tip.

  5. Eric Lind says:

    Hey Chandoo,

    That p-value formula is really great for a statistics person like me.

    What a p-value essentially is, is the probability that the results obtained from a statistical test aren't valid. So for example, if my p value is .05, there's a 5% probability that my results are wrong.

    You can play with this if you install the Data Analysis Toolpak (which will perform some statistical tests for you AND provide the P Value.)

    Let's say for example I've got two weeks of data (separated into columns) with the number of hours worked per day. I want to find out if the total number of hours I worked in week two were really all the different than week one.

    Week1 Week2
    10 11
    12 9
    9 10
    7 8
    5 8

    Go to Data > Data Analysis > T-Test Assuming Unequal Variances > OK

    In the Variable 1 Box, select the range of data for week 1.
    In the Variable 2 Box, select the range of data for week 2.
    Check "Labels"
    In the Alpha box, select a value (in percentage terms) for how tolerant you are of error.

    .05 is the general standard; that is to say I am willing to accept a 95% level of confidence that my result is accuarate.

    Select a range output.

    Excel calculates a number of results: Average (mean) for each week's data, etc.

    You'll notice however that there are two P Values; one-tail and two-tail. (one tail tests are for > or .05), the number of hours I worked in week two is statistically equivalent to the number of hours I worked in week one.

    So here’s a way you might want to use this. You put up a new entry on your blog. You think it’s the best entry ever! So you pull your webstats for this week and compare it to last week. You gather data for each week on the length of time a visitor spends on your website. The question you’re trying to prove statistically is whether there’s an average increase in the amount of time spent on your website this week as compared to last week (as a result of your fancy new blog post). You can run the same statistical test I illustrated above to find out. Incidentally, it matters very little to the stat test whether the quantity of visitors differs or not.

    Anyhow, the Data Analysis toolpack doesn't perform a lot of stat tests that folks like me would like to have access to. In those cases I have to either use different software, or write some very complicated mathematical formulas. Having this p-value formula makes my life a LOT easier!

    Thanks!

    Eric~

  6. Balaji OS says:

    Fantastic stuf..One line explanation is cool.
    Thanks to all the contributors

    OS

  7. Locke says:

    Take FirstName, MI, LastName in access (you can fix it to work in excel) capitalize first letter of each and lowercase the rest and add ". " if MI exists then same for last name:
    Full Name: Format(Left([FirstName],1),">") & Format(Right([FirstName]),Len([FirstName])-1),"") & ". ","") & Format(Left([LastName],1),">") & Format(Right([LastName],Len([LastName])-1),"<")

    I teach excel, access, etc etc for a living and i have my access students build this formula one step at a time from the inside out to show how formulas can be made even if it looks complicated. Yes I know I could just do IsNull([MI]) and reverse the order in the Iif() function but the point here is to nest as many functions as possible one by one (also I illustrate how it will fail without the Not() as it is)

  8. Johan says:

    Extract the month from a date
    The easiest formula for this is =MONTH(a1)
    It will return a 1 for January, 2 for February etc.

  9. anjali says:

    if in a column we write the value of total person for eg. 10 if we spent 1.33 paise each person then how we get total amount in next column and the result will in round form plzzzzz solve my problem sir................... thank u

  10. Hui... says:

    @Anjali

    If the value 10 is in B2 and 1.33 paise is in C2 the formula in D2 could be =B2*C2

    If the values are a column of values you can copy the formula down by copy/paste or drag the small black handle at the bottom right corner of cell D2

  11. sajid says:

    kindly share with me new forumulas.

  12. Biswajit Baidya says:

    How to convert a figure like 870.70 into 870 but 871.70 into 880 using excel formula ? Please help.

Leave a Reply