Gantt Charts – Project Management Using Excel [Part 1 of 6]

Share

Facebook
Twitter
LinkedIn

Starting this week we are starting a new series of posts on project management using Microsoft excel. I have been working in various projects in the last 6 years and almost in all cases we have been using excel to manage, measure and track various aspects of project. These posts represent few of the things related to project management using excel that I have learned over the years.

Part 1: Preparing & tracking a project plan using Gantt Charts
Team To Do Lists – Project Tracking Tools
Project Status Reporting – Create a Timeline to display milestones
Time sheets and Resource management
Issue Trackers & Risk Management
Project Status Reporting – Dashboard
Bonus Post: Using Burn Down Charts to Understand Project Progress

Excel, because of its grid nature provides a great way to prepare and manage project plans. In this part of the project management using Microsoft excel series we will learn how to prepare and track a project plan using gantt chart in excel.

Preparing a project plan

Not all project plans are same. But most of the project plans have a list of,

  • All activities / phases of project
  • Planned start date of the activity
  • Planned duration of the activity

From tracking perspective, we can add the following,

  • Actual start date of the activity
  • Actual duration of the activity
  • % of the activity completed as of date

As you can see, excel provides a great way to manage such plan. Look at an example project plan made in excel.
Gantt Chart - Excel - Project Plan

But the above plan is more or less static. Using Excel’s features we can make a dynamic gantt chart that can,

  • Update the Gantt chart when dates change
  • Display a separate bar that will grow based on the % completion of each activity
  • Highlight current week / day in a subtle way

In essence, we will create something like this:

Steps for preparing an Gantt Chart

  1. First make the above layout in a new excel sheet
  2. Then we will add several columns in the end, one for each day (or week or month) of the project
  3. We will also designate 3 cells say $N$5, $Y$5, $AL$5 where we will maintain the following values,
    1. In cell $N$5, a selection option that will change the plan between “planned” and “actual” dates
    2. In cell $Y$5, a symbol that we can use to display finished portion of work
    3. In cell $AL$5, where we can enter the current week (or day or month)
  4. Now we will do some conditional formatting (ahem!) that will highlight a particular cell in the grid,
    1. If $N$5 has “Planned” and cell is between planned date and planned date + planned duration
    2. Else, cell is between actual date and actual date + actual duration
  5. We will also write formulas in all the cells (same formula pasted over the entire range) which displays a symbol like solid rectangle. For finding out if we should fill in the symbol or not, we use the % completed column of the gantt chart. Figuring out this formula is part of your home work. 😉
  6. Finally we will adjust formatting like column widths, fonts, colors etc. and freeze top row so that it is easy to scroll and still know what you are looking at.

Once you prepare such plan it is easy to track, find out the status of individual activities and take necessary corrective actions as needed.

Download Excel Gantt Chart Template and Make your own project plan

Feel free to download gantt chart project plan template and make your own project plans using Microsoft Excel.

Download 7 Gantt Chart Templates and 17 other Project Management Templates for Excel – Click here

What next?

In the next part of this series we will understand how to manage day to day activities of projects using to do lists in excel.

Resources for Project Managers

Check out my Project Management using Excel page for more resources and helpful information on project management.

Also check out below pages:

Your Thoughts and Suggestions

Do you work a lot on project management activities? Do you find this content useful? share your feedback and experiences through comments.

Project Management Templates for Excel

Facebook
Twitter
LinkedIn

Share this tip with your colleagues

Excel and Power BI tips - Chandoo.org Newsletter

Get FREE Excel + Power BI Tips

Simple, fun and useful emails, once per week.

Learn & be awesome.

Welcome to Chandoo.org

Thank you so much for visiting. My aim is to make you awesome in Excel & Power BI. I do this by sharing videos, tips, examples and downloads on this website. There are more than 1,000 pages with all things Excel, Power BI, Dashboards & VBA here. Go ahead and spend few minutes to be AWESOME.

Read my storyFREE Excel tips book

Overall I learned a lot and I thought you did a great job of explaining how to do things. This will definitely elevate my reporting in the future.
Rebekah S
Reporting Analyst
Excel formula list - 100+ examples and howto guide for you

From simple to complex, there is a formula for every occasion. Check out the list now.

Calendars, invoices, trackers and much more. All free, fun and fantastic.

Advanced Pivot Table tricks

Power Query, Data model, DAX, Filters, Slicers, Conditional formats and beautiful charts. It's all here.

Still on fence about Power BI? In this getting started guide, learn what is Power BI, how to get it and how to create your first report from scratch.

21 Responses to “Distinct count in Excel pivot tables”

  1. Al says:

    The distinct count option works well but I have found that if I have a date field and want to group by year, month, etc. that option seems to be disabled. I need to do both, distinct count and group by year/month.
    Example data; sales orders with item quantities with dates.
    Challenge; sum the item quantities, count the distinct orders and group by month. How do I do this?
    Perhaps that's not possible due to the grouping?

    • Chandoo says:

      @Al... When you use data model based pivots, you cannot group values manually anymore. Why not use Excel 2016's default date grouping option? In this case we have just a few dates, so Excel is not grouping them, but if you have an year's worth of data, when you make the pivot with date in the row label area, Excel automatically groups them. If you have fewer dates or want to use your own grouping, just create a table with all dates, add columns with month, week, year etc. Then connect this table (these types of tables are usually called as calendar tables) to your data on date field as a relationship. Now you can create reports by month, quarter etc easily.

      • Dan says:

        Is this the only way to do it in 2013? I find it rather cumbersome to have to create another data table listing dates with the another column for MONTH() and YEAR() to be able to summarise data for senior level...

        • Chandoo says:

          I know people find adding calendar tables cumbersome, but it is a best practice and let's you add more layers of analysis quite easily. For example, adding analysis by weekday vs. weekend or by financial quarter or YTD calculations (you would need either Power Pivot DAX or some very carefully setup pivot table value field settings)

  2. NC says:

    I had absolutely no idea this was possible. Very useful, nice work!

  3. Pete says:

    Doesn't work for 2010 version though (or at least not my works version)

    • NARAYAN says:

      Hi ,

      The post has the following in it :

      These instructions work only in Excel 2016, Office 365 and Excel 2013.

  4. Sarah says:

    when i have 2 different Pivot tables, one without the enabled “Add this data to data model” option, and the other one with it enabled.. is there anyway i can link slicers between them?
    if the answer is NO,, what to do ?

  5. Edgar says:

    Quick note, the “Add this data to data model” option is not available for the Mac version.

  6. Steve Curtis says:

    perhaps outside scope of this article but I have found when I attempt to create a pivot table from an external data source (connection to a sql view) the "Add this data to data model" becomes greyed out. Anybody experienced and found a solution so I can start getting distinct count in my pivot tables?

  7. Kelly Nanfito says:

    Is there a way to still add a calculated field when using distinct count?

  8. Luna says:

    I found I can't change the date source after tick the " add this data to the data model", can you help to adv how to change the date source in such case?

  9. Chris says:

    Is there a way to update the source once you have added to the data model? I receive a new spreadsheet weekly and would like to update the connection so my tables pull from the new source.

  10. Ankit Moral says:

    A big Thank you. It worked.

  11. Mohapi says:

    Hi, have survey data that I need to analyze but the challenge is that my key fields are showing horizontally. I tried to transpose the fields using Power Query, but unfortunately the new fields are returning same values on a pivot table despite using distinct values

  12. sorina says:

    How I can a do a pivot table with discount conts in some columns and then generate shor report filter pages. pls it drives crazy

  13. ira says:

    Hi. Why grand total pivot of distinct count is 13? shouldn't it be 67?

  14. Asia says:

    Great Answer! Saved me lots of time!
    Thank you!!!

  15. Suresh says:

    Worked awesome! Thanks!!

  16. Mayank says:

    Hi Chandoo,
    I am using pivot tables for distinct count and now I need to update them with new set of data. But when I update the source data, all the columns and formatting of Pivot table disappears and I need to build it from Scratch.

    Is there a possibility that I can update the source data with new rows added and also retain my pivot tables?

Leave a Reply