Gantt Charts – Project Management Using Excel [Part 1 of 6]

Share

Facebook
Twitter
LinkedIn

Starting this week we are starting a new series of posts on project management using Microsoft excel. I have been working in various projects in the last 6 years and almost in all cases we have been using excel to manage, measure and track various aspects of project. These posts represent few of the things related to project management using excel that I have learned over the years.

Part 1: Preparing & tracking a project plan using Gantt Charts
Team To Do Lists – Project Tracking Tools
Project Status Reporting – Create a Timeline to display milestones
Time sheets and Resource management
Issue Trackers & Risk Management
Project Status Reporting – Dashboard
Bonus Post: Using Burn Down Charts to Understand Project Progress

Excel, because of its grid nature provides a great way to prepare and manage project plans. In this part of the project management using Microsoft excel series we will learn how to prepare and track a project plan using gantt chart in excel.

Preparing a project plan

Not all project plans are same. But most of the project plans have a list of,

  • All activities / phases of project
  • Planned start date of the activity
  • Planned duration of the activity

From tracking perspective, we can add the following,

  • Actual start date of the activity
  • Actual duration of the activity
  • % of the activity completed as of date

As you can see, excel provides a great way to manage such plan. Look at an example project plan made in excel.
Gantt Chart - Excel - Project Plan

But the above plan is more or less static. Using Excel’s features we can make a dynamic gantt chart that can,

  • Update the Gantt chart when dates change
  • Display a separate bar that will grow based on the % completion of each activity
  • Highlight current week / day in a subtle way

In essence, we will create something like this:

Steps for preparing an Gantt Chart

  1. First make the above layout in a new excel sheet
  2. Then we will add several columns in the end, one for each day (or week or month) of the project
  3. We will also designate 3 cells say $N$5, $Y$5, $AL$5 where we will maintain the following values,
    1. In cell $N$5, a selection option that will change the plan between “planned” and “actual” dates
    2. In cell $Y$5, a symbol that we can use to display finished portion of work
    3. In cell $AL$5, where we can enter the current week (or day or month)
  4. Now we will do some conditional formatting (ahem!) that will highlight a particular cell in the grid,
    1. If $N$5 has “Planned” and cell is between planned date and planned date + planned duration
    2. Else, cell is between actual date and actual date + actual duration
  5. We will also write formulas in all the cells (same formula pasted over the entire range) which displays a symbol like solid rectangle. For finding out if we should fill in the symbol or not, we use the % completed column of the gantt chart. Figuring out this formula is part of your home work. 😉
  6. Finally we will adjust formatting like column widths, fonts, colors etc. and freeze top row so that it is easy to scroll and still know what you are looking at.

Once you prepare such plan it is easy to track, find out the status of individual activities and take necessary corrective actions as needed.

Download Excel Gantt Chart Template and Make your own project plan

Feel free to download gantt chart project plan template and make your own project plans using Microsoft Excel.

Download 7 Gantt Chart Templates and 17 other Project Management Templates for Excel – Click here

What next?

In the next part of this series we will understand how to manage day to day activities of projects using to do lists in excel.

Resources for Project Managers

Check out my Project Management using Excel page for more resources and helpful information on project management.

Also check out below pages:

Your Thoughts and Suggestions

Do you work a lot on project management activities? Do you find this content useful? share your feedback and experiences through comments.

Project Management Templates for Excel

Facebook
Twitter
LinkedIn

Share this tip with your colleagues

Excel and Power BI tips - Chandoo.org Newsletter

Get FREE Excel + Power BI Tips

Simple, fun and useful emails, once per week.

Learn & be awesome.

Welcome to Chandoo.org

Thank you so much for visiting. My aim is to make you awesome in Excel & Power BI. I do this by sharing videos, tips, examples and downloads on this website. There are more than 1,000 pages with all things Excel, Power BI, Dashboards & VBA here. Go ahead and spend few minutes to be AWESOME.

Read my storyFREE Excel tips book

Overall I learned a lot and I thought you did a great job of explaining how to do things. This will definitely elevate my reporting in the future.
Rebekah S
Reporting Analyst
Excel formula list - 100+ examples and howto guide for you

From simple to complex, there is a formula for every occasion. Check out the list now.

Calendars, invoices, trackers and much more. All free, fun and fantastic.

Advanced Pivot Table tricks

Power Query, Data model, DAX, Filters, Slicers, Conditional formats and beautiful charts. It's all here.

Still on fence about Power BI? In this getting started guide, learn what is Power BI, how to get it and how to create your first report from scratch.

26 Responses to “Get busy this weekend, with OR XOR AND [Excel Homework]”

  1. Stef@n says:

    first solution for AND
    The two numbers are in A1 and B1
    = SUBSTITUTE (SUBSTITUTE (A1+B1*9*9, 9, 1), 8, 0)
    regards
    Stef@n

  2. Stef@n says:

    next solution for OR
    =1*SUBSTITUTE (A1+A2;2;1)

    regards
    Stef@n

  3. Stef@n says:

    last solution for XOR
    =1*SUBSTITUTE (A1+A2;2;0)

    regards
    Stef@n

  4. Irvine says:

    Or you could make use of the VBA logical operators!

    Define the following as custom functions
    Public Function BITXOR(x As Long, y As Long)
    BITXOR = x Xor y
    End Function

    Public Function BITAND(x As Long, y As Long)
    BITAND = x And y
    End Function

    Public Function BITOR(x As Long, y As Long)
    BITOR = x Or y
    End Function

    and then use them such:
    A B =BITOR(A,B) =BITAND(A,B) =BITXOR(A,B)
    0101 0100 0101 0100 0001

  5. Stef@n says:

    an another solution for AND
    =1*SUBSTITUTE (SUBSTITUTE (A1+A2;1;0);2;1)

    note:
    the binary numbers are in A1 and A2 !
    regards
    Stef@n

  6. Shair says:

    I was obviously playing hooky at the beach during the bit-wise math lesson – you lost me at “Understanding bit-wise operations” 🙂

  7. Anup Agarwal says:

    After looking at the above solutions, I find my solution silly, but still:

    For the following formulae,
    Row 1: headers,
    Row 2: OR
    Row 3: AND
    Row 4: XOR

    Column 1: Input 1
    Column 2: Input 2
    Column 3: Result

    OR
    {=SUM(IF(MID(A2,ROW(OFFSET($A$1,0,0,LEN(A2),1)),1)+MID(B2,ROW(OFFSET($A$1,0,0,LEN(B2),1)),1)>0,1,0)*10^(LEN(A2)-ROW(OFFSET($A$1,0,0,LEN(B2),1))))}

    AND
    {=SUM(IF(MID(A3,ROW(OFFSET($A$1,0,0,LEN(A3),1)),1)+MID(B3,ROW(OFFSET($A$1,0,0,LEN(B3),1)),1)=2,1,0)*10^(LEN(A3)-ROW(OFFSET($A$1,0,0,LEN(B3),1))))}

    XOR
    {=SUM(IF(MID(A4,ROW(OFFSET($A$1,0,0,LEN(A4),1)),1)+MID(B4,ROW(OFFSET($A$1,0,0,LEN(B4),1)),1)=1,1,0)*10^(LEN(A4)-ROW(OFFSET($A$1,0,0,LEN(B4),1))))}

  8. Hui... says:

    @Anup
    Please don't consider your solution silly
    Firstly, You are the 3rd person to submit an answer
    Secondly, The best formula/function is the one that you know and understand.

  9. Michael Azer says:

    I think I have a very tedious solution, which people won't have the patience to do except in small numbers.

    I used the same problem setup as "Anup Agarwal"

    AND =IF(AND(MID(B2,1,1)="1",MID(C2,1,1)="1"),1,0)&IF(AND(MID(B2,2,1)="1",MID(C2,2,1)="1"),1,0)&IF(AND(MID(B2,3,1)="1",MID(C2,3,1)="1"),1,0)&IF(AND(MID(B2,4,1)="1",MID(C2,4,1)="1"),1,0)

    OR =IF(OR(MID(B3,1,1)="1",MID(C3,1,1)="1"),1,0)&IF(OR(MID(B3,2,1)="1",MID(C3,2,1)="1"),1,0)&IF(OR(MID(B3,3,1)="1",MID(C3,3,1)="1"),1,0)&IF(OR(MID(B3,4,1)="1",MID(C3,4,1)="1"),1,0)

    =IF(OR(AND(MID(B4,1,1)="1",MID(C4,1,1)="0"),AND(MID(B4,1,1)="0",MID(C4,1,1)="1")),1,0)&IF(OR(AND(MID(B4,2,1)="1",MID(C4,2,1)="0"),AND(MID(B4,2,1)="0",MID(C4,2,1)="1")),1,0)&IF(OR(AND(MID(B4,3,1)="1",MID(C4,3,1)="0"),AND(MID(B4,3,1)="0",MID(C4,3,1)="1")),1,0)&IF(OR(AND(MID(B4,4,1)="1",MID(C4,4,1)="0"),AND(MID(B4,4,1)="0",MID(C4,4,1)="1")),1,0)

  10. Michael Azer says:

    Sorry my last post was totally messed up

    AND
    =IF(AND(MID(B2,1,1)="1",MID(C2,1,1)="1"),1,0)&IF(AND(MID(B2,2,1)="1",MID(C2,2,1)="1"),1,0)&IF(AND(MID(B2,3,1)="1",MID(C2,3,1)="1"),1,0)&IF(AND(MID(B2,4,1)="1",MID(C2,4,1)="1"),1,0)
    OR
    =IF(OR(MID(B3,1,1)="1",MID(C3,1,1)="1"),1,0)&IF(OR(MID(B3,2,1)="1",MID(C3,2,1)="1"),1,0)&IF(OR(MID(B3,3,1)="1",MID(C3,3,1)="1"),1,0)&IF(OR(MID(B3,4,1)="1",MID(C3,4,1)="1"),1,0)
    XOR
    =IF(OR(AND(MID(B4,1,1)="1",MID(C4,1,1)="0"),AND(MID(B4,1,1)="0",MID(C4,1,1)="1")),1,0)&IF(OR(AND(MID(B4,2,1)="1",MID(C4,2,1)="0"),AND(MID(B4,2,1)="0",MID(C4,2,1)="1")),1,0)&IF(OR(AND(MID(B4,3,1)="1",MID(C4,3,1)="0"),AND(MID(B4,3,1)="0",MID(C4,3,1)="1")),1,0)&IF(OR(AND(MID(B4,4,1)="1",MID(C4,4,1)="0"),AND(MID(B4,4,1)="0",MID(C4,4,1)="1")),1,0)

  11. Stephen says:

    @stefan,
    I just couldn't get your solutions to work.
    01010101010 + 01010101110 = 02020210120
    what am i doing wrong?

  12. Stephen says:

    @anup
    ...I got yours to work!

  13. Rich says:

    @Stephen - I get the same, but Stef@an's second solution for AND does work (at least for the test cases I used)

  14. Stef@n says:

    @ Stephen / Rich
    yes , you are right ! - only this works:

    OR
    =1*SUBSTITUTE (A1+A2;2;1)
    XOR
    =1*SUBSTITUTE (A1+A2;2;0)
    AND
    =1*SUBSTITUTE (SUBSTITUTE (A1+A2;1;0);2;1)

  15. Michael Azer says:

    @Stef@n - You're answer is really smart, I never knew about the substitute function before. Great Work!

  16. Stef@n says:

    Thx Michael 🙂
    yes - it is simply easy 😉
    if you add 1 and 1 - excel calculate 2
    and then you have to substitute the 2 - new = 0 respectively 1

  17. Rob says:

    Here is a good resource for people wanting to learn binary and hexadecimal.
    http://justwebware.com/bitwise/bitwise.html

  18. Kyle McGhee says:

    Three that weren't asked for:
    NOT
    =SUBSTITUTE(SUBSTITUTE(SUBSTITUTE(A1+A2,0,3),1,0),3,1)

    EQV
    =SUBSTITUTE(SUBSTITUTE(SUBSTITUTE(SUBSTITUTE(A1+A2,0,3),2,3),1,0),3,1)

    IMP
    =SUBSTITUTE(SUBSTITUTE(A1+SUBSTITUTE(SUBSTITUTE(SUBSTITUTE(A2,0,3),1,0),3,1),0,1),2,0)

    (was using Daniel Ferry's bitwise file to verify against)

  19. Q says:

    @ Kyle

    Not only takes one parameter and inverts 0 -1 and 1-0

    Took out the +A2
    =SUBSTITUTE(SUBSTITUTE(SUBSTITUTE(A1,0,3),1,0),3,1)

  20. Great solutions!

    I'll add two:

    NAND =1*SUBSTITUTE (A1+A2,2,0)

    NOR=1*SUBSTITUTE(SUBSTITUTE (SUBSTITUTE(A1+A2,0,2),1,0),2,1)

  21. John Fuller says:

    This will work for binary numbers of any size (although the text format mask will have to have as many zeroes as there are digits in the longest addend)

    Assume binary #s are in C35 & C36, then add and format as text in C37:
    =TEXT(C36+C35,"000000000000")
    -sum- = 101112211112

    AND - SUBSTITUTE 0s for 1s in -sum-, then sub 1s for 2s
    =SUBSTITUTE(SUBSTITUTE(C37,"1","0"),"2","1")

    OR - sub 1s for 2s in -sum-
    =SUBSTITUTE(C37,"2","1")

    XOR - sub 0s for 2s in -sum-
    =SUBSTITUTE(C37,"2","0")

  22. Shane says:

    Just wandered by:

    AND:

    =SUBSTITUTE(A1+A2,1,0)/2

  23. Ronald Vonk says:

    Hi Chandoo,

    I am not (yet) really into bitwise calculation, but I am looking for a way to speed up my vba calculation with very big numbers. Would is ben convenient to use bitwise notation for this?

    Best regards,

    Ronald (the Netherlands)
    p.s. love your country!

Leave a Reply