Pareto Charts – How to do pareto analysis using Excel?

Share

Facebook
Twitter
LinkedIn

A Pareto chart or pareto graph displays the importance of various factors in decreasing order in columns along with cumulative importance in a line. Pareto charts are often used in quality control to display most common reasons for failure, customer complaints or product defects.

The principle behind pareto charts is called as pareto principle or more commonly the 80-20 rule. According to wikipedia,

The Pareto principle (also known as the 80-20 rule,[1] the law of the vital few, and the principle of factor sparsity) states that, for many events, roughly 80% of the effects come from 20% of the causes.

The pareto chart is a great way to do the pareto analysis. Today, we will learn how to use excel to make a pareto chart.

See an example pareto chart of visits to this website:

pareto chart example

(Please note that in this example, the 80/20 rule does not hold as I have chosen very small sample of data. In reality, the 80/20 principle applies to my website as well)

Making a Pareto Chart in Excel

In order to make the pareto chart in excel, first you must have the data ready. Once we have the values for each cause, we can easily calculate cumulative percentages using excel formulas. We will also require a dummy series to display the “cutoff %” in the Pareto chart.

I have arranged the data in this format. You can choose any format that works for you.

Pareto analysis - data

Once you have the data ready, making the pareto chart is a simple 5 step process.

1. Make a column chart using cause importance data

Make a column chart using cause importance data
In our case, we select the first 2 columns in the above table and then make a new column chart.

2. Add the cumulative %s to the Pareto Chart as a line

Add the cumulative %s to the Pareto Chart as a line
Select the third column, press ctrl+c (copy). Now select the chart and press ctrl+v (paste). Excel will add another column series to the chart. Just select it and change the series chart type to “line chart”. Learn more about combining 2 different chart types in excel combo charts.

3. Move the cumulative %s line to secondary axis

Move the cumulative %s line to secondary axischange to secondary axis

Select the line chart, go to “format data series” (you can also press ctrl+1) and change the axis for this chart series from “primary” to “secondary”.

4. Add the cut-off % to the pareto chart

Add the cut-off % to the pareto chart
Select the fourth column in our data table, copy and paste it in the chart. This should ideally be pasted as a new line chart. If not, follow step 2 for this as well.

5. Finally, adjust formatting to make the final pareto chart

Finally, adjust formatting to make the final pareto chart
Now, our basic pareto chart is ready. We should adjust the chart formatting to make it more presentable. Once you are done, the final output will be something like above chart.

Download the Pareto Chart Template in Excel

Click here to download the excel pareto chart template.

When to use Pareto Chart?

Pareto charts can be used,

  • During quality control to analyze the causes of defects and failures
  • When you want to focus your resources on few important items from a large list of possibles
  • To tell the story that attacking problem A might be better than solving problem C, D and F

Pareto charts and pareto analysis has great practical uses for almost anyone in a managerial role.

Have you used Pareto analysis or Pareto charts in your job?

Pareto principle is the first real management lesson I have learned during my MBA. It is the topic for my first presentation too. During the presentation, Anoop, my jovial team mate said, “80-20 principle can be tested anywhere. For eg. in most parties 80% of the beer will be consumed by 20% of people”, and the whole class started laughing.

Jokes apart, I think pareto principle is a very powerful idea told in an extremely simple way. I use the pareto analysis to find best way to invest my time. What about you? Tell me about your experiences of using pareto analysis using comments.

Related Material:

Facebook
Twitter
LinkedIn

Share this tip with your colleagues

Excel and Power BI tips - Chandoo.org Newsletter

Get FREE Excel + Power BI Tips

Simple, fun and useful emails, once per week.

Learn & be awesome.

Welcome to Chandoo.org

Thank you so much for visiting. My aim is to make you awesome in Excel & Power BI. I do this by sharing videos, tips, examples and downloads on this website. There are more than 1,000 pages with all things Excel, Power BI, Dashboards & VBA here. Go ahead and spend few minutes to be AWESOME.

Read my storyFREE Excel tips book

Overall I learned a lot and I thought you did a great job of explaining how to do things. This will definitely elevate my reporting in the future.
Rebekah S
Reporting Analyst
Excel formula list - 100+ examples and howto guide for you

From simple to complex, there is a formula for every occasion. Check out the list now.

Calendars, invoices, trackers and much more. All free, fun and fantastic.

Advanced Pivot Table tricks

Power Query, Data model, DAX, Filters, Slicers, Conditional formats and beautiful charts. It's all here.

Still on fence about Power BI? In this getting started guide, learn what is Power BI, how to get it and how to create your first report from scratch.

28 Responses to “Team To Do Lists – Project Tracking Tools using Excel [Part 2 of 6]”

  1. [...] & tracking a project plan using Gantt Charts Team To Do Lists - Project Tracking Tools Part 3: Preparing a project time line [upcoming] Part 4: Time sheets and Resource management [...]

    • Jacobus says:

      the templates are great (I bought the combo).
      What I'm missing is a way to have the project gantt chart and reporting with the data per resource, in such a way that I can also show the occupation per resource on an extended gantt chart.

      So with hours entered per person per project or sub-activity, to show a gantt chart of how many hours/days a person spent on which project (or plans to spend).

  2. [...] from: Team To Do Lists - Project Tracking Tools using Excel [Part 2 of 6] 25 Jun 09 | [...]

  3. ross says:

    Hi Chandoo,

    Funny I have a post on the value of MS project lined up which I will post when the current monster project I'm working on finishes and I get some free time!

    I'm not sure this would help with any of the projects I've worked on, closing down a to do list seems like more effort than it's worth, but it might be useful for some things. I guessing it doesn't, but does the time stamp not update when you recalculate the work book?

    keep up the good work!
    Ross

  4. Chandoo says:

    @Ross.. Thanks for sharing your ideas... I think to do lists are a great way to keep up with project activities and ensure accountability from individual team members, when they are implemented right.

    "I guessing it doesn’t, but does the time stamp not update when you recalculate the work book?"

    Your guess is right. When you change the calculation mode to "iterative", excel takes care of the nittygritties and retains older values in circular references in formulas.

  5. [...] Project Management in Excel [New Series] - Gantt Charts | To Do Lists [...]

  6. [...] & tracking a project plan using Gantt Charts Team To Do Lists - Project Tracking Tools Project Status Reporting - Create a Timeline to display milestones Part 4: Time sheets and Resource [...]

  7. Tam says:

    Hi Chandoo,
    The template give me lot of convenience to monitor the thing to do. It simple. Thank You

  8. [...] & tracking a project plan using Gantt Charts Team To Do Lists - Project Tracking Tools Project Status Reporting - Create a Timeline to display milestones Part 4: Time sheets and Resource [...]

  9. [...] make sure you have read the first 4 parts of the series - Making gantt charts [project planning], team todo lists [project tracking], project time lines chart [reporting] and Timesheets and Resource Management using Excel. Also [...]

  10. Brian says:

    Chandoo,

    I really do not see any befit to this function in Excel unless it was somehow tied into some other chart. That is say a scheduled activities % complete is based on the to-do list.

    The only way this chart would be useful is if no one was assigned none dependent task that could be done by anyone. The cases were both of these conditions are true are so few and far between it really makes this chart worthless.

  11. Chandoo says:

    @Brian... Once you have a todo list up and running, it is easy to get metrics out of it. I didnt propose it as it might look a bit too micro-management-ish.

    I am able to understand what you meant by "The only way this chart would be useful is if no one was assigned none dependent task that could be done by anyone. The cases were both of these conditions are true are so few and far between it really makes this chart worthless."

    Can you explain?

  12. Brian says:

    "Chandoo"

    What I mean is this. Lets say you have 10 task which are part of one activity/WBS that is in your schedule. One there are very few cases were many people would be assigned to complete this one scheduled activity with no direction being given who should what of the 10 task. It is poor management, and the task 90% of the time would not get done in a timely manner if say 4 people were responsible. Secondly, you are assuming all 10 task are independent of each other. You might need to do task 1 thru 3 before you can do task 4, and to do task 7 you might need to do 4 and 6. Thirdly, the time it would take to compile and then fill out the to-do-list even in limited applications is really not worth it.
    I just see almost no applications why a team would need to inform others separate from the schedule that they have completed a task on a to-do list unless anyone of the 4 people could of completed that task.

    My point is, there might be a few very limited applications for this type of list but this list would be worthless as a Project Management tool in every other case.

    However, change this from a to-do-list to a document change log and it is perfect. Instead of to-do it is the documents name or summary of what changed in the document. The person is who edited the document, and the time stamp is when they checked it in. But I do not know why you would use excel when there is free software you can use commercially that is 10 times better that does document management.

    I think using excel to do Project Management over a real Project Management application is a bad idea. Unless you are running a very small, simple project, the time and effort is a lot more to use excel compared to the cost of the Project Management software.

    This comes back to my point, I love your site, however, just because you can do something in excel does not mean you should do it. To often the time it takes to use excel is wasted 10 times over from the cost of doing it in an application designed to for the specific application.

  13. Chandoo says:

    @Brian: The todo list mentioned here is meant to keep track of all the tasks for which detailed planning is not necessary but some sort of tracking is needed. These are not be confused with project activities (a la gantt chart).

    I like your suggestion about using this as a document tracker. Pretty cool use.

    Coming to your point about excel as a real project management tool, well, I have my views, but in a serious project environment, it would surely payoff to have a dedicated project management application.

  14. [...] & tracking a project plan using Gantt Charts Team To Do Lists – Project Tracking Tools Project Status Reporting – Create a Timeline to display milestones Time sheets and Resource [...]

  15. Somnath says:

    Chandoo,

    Wonder how the timestamp column will maintain its previous data. Both Today() and Now() functions will update as and when the next timestamp happens.

  16. [...] Preparing & tracking a project plan using Gantt Charts Part2: Team To Do Lists – Project Tracking Tools Part3: Project Status Reporting – Create a Timeline to display milestones Part4: Time sheets and [...]

  17. Tate says:

    I've combined this with the issue tracker since I like the automatic date stamp, but one thing I'm noticing is that I can't replicate the chart that goes along with the issue tracker because the cells that are referenced have the formula that inserts the time stamp instead of a the actual date value. All the dates of the last 30 days display 0 when they should have a value.

    Is there a way around this?

  18. Mitch says:

    I have edited the chart so that my team members can update the percentage completion of the assigned tasks. When the cell is updated, i would like the time stamp to update. How would I manipulate the formula to update whenever the drop-down list is changed?

  19. Excel is great however sometimes you need to get a better idea of what tasks each person on your team is working on at any given time. We've developed a web app that can do just that! Each person has a list of tasks, listed in the order they have to complete them.

  20. Yukti Kumar says:

    HII,

    I want to expand the database through excel where i am working on 11 cities as of now and i want to expand it upto 50 cities and hence forth the data related to it will also expand so i want to make it precise where i can get updates also that this work is required to be done at that particular day or date

  21. BudB says:

    Thanks for making all of this information available for free. I am currently using excel to track everything for the first time. I later plan to output our information here with a more visual presentation. Wish me luck!

  22. Learner says:

    Can some one point me out to some additional direction on the "Who Finished it?" column? Something more 'basic' for a newbie excel guy? lol I got everything else working on this tutorial but that column. I can't seem to recreate it and I know a lot of it is due to lack of knowledge with VB code. I'd like to recreate this column very much 🙁

  23. Nishad says:

    Dear Chandoo,
    Thanks for the team to do list, kindly let me know how to set the column who " finished it " from another work sheet

  24. Srihari says:

    Hi Chandoo,

    Unable to download it - can you please check the link and confirm.

  25. Aryona says:

    Great inhisgt! That's the answer we've been looking for.

  26. Tushar Kacha says:

    Hi Team,

    I know u all are the best programmers in the world!!! that's I am here to rectify my issues. here is my question please ans me as soon as possible before 8-3-2017 its really urgent.

    I have a project named the production tracker.

    1) I require the user form which shows the names of the Associates which are linked to the different tracks. when the user is selected the particular track related details and dropdowns should appear.

    2) I need to track the associate needs how much of the time to complete the particular task. with start stop and pause and resume timer.

    3) It should display the daily count of the production and save the data to the another Excel file.

    this production tracker should save all the data no matter how many people logs in into it.

    Please help me for this it will be very appreciated.

    you can directly email me on my mail ID: tusharkch694@gmail.com

Leave a Reply