Yesterday in Formula Forensics 008 we looked at Elkhans MaxIf problem.
However the solution/formula as presented is the final solution to his problem.
Elkhans original worksheet contained other problems and today we will look at this:
I have attached the orginal file as a sample file you can Download Here.
You will see that the MaxIf cell F13 is returning 0, where it should be showing 0.246
Houston, We’ve Had a Problem!
Cell F13 has the same formula we looked at in yesterday’s Formula Forensics: =MAX(IF((Parameter_3=D13)*(Parameter_4=E13),Parameter_5,0))
A quick check of the formula reveals that everything was technically right with the formula, yet the answer is wrong?
To solve this I tried several steps which is the topic of this post:
Examine the logic of the If’s Criteria
The formula =MAX(IF((Parameter_3=D13)*(Parameter_4=E13),Parameter_5,0)) works by calculating the maximum value from the If array.
So step 1 was to look at the logic in the If’s Criteria
That is (Parameter_3=D13)*(Parameter_4=E13)
In cell F15 I entered = (Parameter_3=D13)*(Parameter_4=E13) followed by F9
Excel returns: = {0;0;0;0;0;0;0;0;0;0;0}
This tells me that none of the Cells match the criteria, strange?
Yet manually I can see 4 matching records, below:
Check Cell Length
The next quick step was to look at the length of the text in each cell.
In Column I, I added a =Len(E2) and copied down, there was only 2 characters in each cell, this step eliminated leading or trailing spaces.
Retype the Data
Elkham supplied the source data in an Excel file.
But the Criteria was manually typed by me.
So the next step was to retype some of the original data in Cell E2
Wow an Answer, So obviously there was a difference?
What is Wrong Here?
So obviously there was a difference between the C1 in cell E2 and the C1 in cell E13?
I checked this in 3 ways
1. Type the value “C1” into Cell E2, without the quotes
This returned an answer 0.08 from F2 as it should have.
2. Copy an old “C1” value to E13
This resulted in the correct answer of 0.246 in F13
3. Use a quick Formula
Entering a quick formula
In F17 type =E2=E13
Excel returns False
Showing that the value of cell E2 does not match E13
So what is in E2:E12 ?
As I had typed the values into the Criteria Cells D13:E13, I knew what they were, they were a plain and simple “C1”
So what was in E2:E12 ?
Next step was to look at the Ascii values of the 2 characters in Column E.
In K2: =Code(Left(E2,1))
In L2: =Code(Right(E2,1))
Copy both down to Row 13
Bingo !
The Character C in cell E2 wasn’t the same as the Character C in E13 ?
Yet both cells contained a Calibri Font.
If I now type in a spare cells:
F18 =Char(63), Excel displays a “?”
F19 =Char(67), Excel displays a “C”
Yet Cell E2 is clearly displaying C1 with a First Character Ascii code of 63 which should be a ? mark.
I suspected that it had been copied and pasted from MS Access, So I shot an email back to Elkhan, asking “What the source of the data was?”.
The response came back that “The data had been copied from a Russian (Cyrillic) version of an MS Word File and pasted into an English version of Excel.”
I can’t explain what has happened but somehow the character sets and associated values got scrambled when copied the data from the Russian Word Document into Excel
If you have had experiences like this or can explain what has happened please do so in the comments below:
Solution
The Solution was now easy
Use Search/Replace
Copy the contents of cell E1,
goto Search/Replace or Ctrl H
Find: Paste the contents of Cell E1
Replace with: C1
Conclusions:
- Be careful when receiving data from foreign language files, including word and Excel files
- Check summations based on such data to ensure its integrity
- Be methodical in tracking down problem cells
Lets us know about your Data Transfer Nightmares
Have you had any strange data transfer issues?
Let us know in the comments below.





















13 Responses to “Gantt Box Chart Tutorial & Template – Download and Try today”
Hi Chandoo
As one of your students I have followed your detailed example through with great success. However, Excel is acting in an unexpected way and I wonder if you could take a look?
http://cid-95d070c79aef808e.office.live.com/self.aspx/.Public/Gantt%20Box%20Chart.xlsm
On my version, I have to type 40239 (Which equates to 2 Mar 2010) to get the chart to display 31 May 2010 (which should be 40329)!!??
Have I done something wrong or is Excel acting up?
Thx
Oli
PS Your example file in 2007 displays correctly.
Hi,
I like this idea a lot, but I agree the name is a little drab.
As an American I may just be seeing things, but to me the combination of lines and bars on your chart looks like a bunch of cricket bats.
Maybe you could work that into a catchier name. 🙂
Cheers!
Here is some code I use to keep the axis synched.
It may be useful to some of your readers
It is based on a comment I saw on Daily Dose of Excel.
Function SynchGanttAxis(Cname, lower, upper)
'Sets the X min and X max for Category axis
Application.Volatile
On Error Resume Next
'
'Top Horizontal Axis
With ActiveSheet.Shapes(Cname).Chart.Axes(xlCategory, 1)
.MinimumScale = lower
.MaximumScale = upper
End With
'Bottom Horizontal Axis
With ActiveSheet.Shapes(Cname).Chart.Axes(xlValue, 2)
.MinimumScale = lower
.MaximumScale = upper
End With
End Function
Function SynchVerticalAxis(Cname, lower, upper)
Application.Volatile
On Error Resume Next
' Excel 2007 only
'Right hand vertical axis
With ActiveSheet.Shapes(Cname).Chart.Axes(xlValue, 1)
.MinimumScale = 0
.MaximumScale = upper
End With
End Function
@Oli.. Can you check your file again.. I see 40329...
@Dave: Even I saw things.. the bars actually looked like lollipops. How about calling this lollipop chart - now that would be yummy and goes along the tradition of naming charts after eatables (bar, pie, donut...)
@Bob: Superb stuff... thanks for sharing 🙂
Hi Chandoo
This looks really good and I think it can also be applied to show project phases / milestones.
Question: Thinking further could this be amended to display a project lifecycle (Idea through to Implementation say 7 phases) on one bar / row? Just imagine 20 projects within a programme all on one chart one bar each showing their respective lifecycle stages i.e. on one page.
Idea: As the Gantt Box Chart this is quite intensive to set up re formatting etc how about the added extra of once you have completed this to "Save as template" i.e. saves the formatting and layout of the chart as a template so you can apply to future charts. Simple to do and will save the time formatting etc again and again and again.
Therefore tip: Click on your chart demo and then click on Save As template icon (2007) - edit file name and click on save. Ready to use / apply via Templates in Change Chart Type window.
Thanks and be very interested if the lifecycle question can be resolved
Mike
How embarrassing.
I was obviously suffering from numerical dyslexia. I was one of those days.
@Mike H: You can easily make this chart to work like a generic project lifecycle plan chart. All you have to do is,
1. in a separate sheet define the steps of lifecycle and various dates in a table (with 5 columns for each of the projects you have).
2. now use a control cell to input the project name you want to show in the chart
3. based on the input, use OFFSET Formulas to get the correct data
4. Rest is same as the tutorial above
For more info on the dynamic charting visit http://chandoo.org/wp/tag/dynamic-charts/ and http://chandoo.org/wp?s=OFFSET
Your solution is really smart but in the en Excel isn't meant to do stuff like this. I, as a former PM, always thought is was frustrating that you had to do stuff like this for something simple like a Gantt chart. So I built Tom's Planner. And would like to plug it here. I think it really solves the problem you are trying to solve in the most efficient way. Check out http://www.tomsplanner.com for a free account or play around with the demo.
Hi there,
Chandoo - this is really a very nice and helpfull chart - I adopted it, so I can report a forecast or the delay of a certain task (coming from my role as an auditor for projects).
One topic I´m currently struggeling with: I do have a project lasting for lets say 12 month. For a management reporting, I want to have kind of snapshot, lets say one month back and 2 month in the future. I tried with the offset formula, but failed. Any idea?
Thx
Lopi
[...] Ein viel geliebter Klassiker ist die Erstellung von GANTT-Diagrammen mit Excel. Wir hatten das Thema wiederholt schon hier. Chandoo.org hat sich mal wieder mit einer neuen Variante hervorgetan: Das GANTT-Box-Chart. [...]
[...] [...]
Hi Chandoo - fantastic xls. One thing I can't figure out how to do is adjust the alignment of the vertical axis. I would like to left align so that I could indent to represent sub tasks. Can that be done? Or is there a better way?
I've been trying to work out if there's a way to show weekends on the graph. The closest thing I've got is to add them on a secondary axis, but then I haven't been able to keep both axis lined up together! Any ideas?
Following on from this - is it possible to show things like holidays?