Hi there -
I am having a problem with adding more than 10 projects to the dashboard.
In the Project Details Sheet: I use "insert" command to add more rows, number them (9,10,11,etc.), add the project names as well.
Then I go to the Project Plans Sheet: I copy all of the last Table from Project 10 and Paste that data right next to it skipping two columns as is done in the other sheets.
I then click on the new table (Table 11) and change its name to "Plan11", I also change the formula for the project name from INDEX(lstProjects,10)to INDEX(lstProjects,11)so the table name gets pulled correctly.
When I go back to the Dashboard and look at Project 11 the activity field is blank - like it is not able to pull any info from the Project Plans sheet. Also when I close the file - I get a runtime error '9' - Subscript out of Range message.
Pls help me work this out. I would really like to use this for more than 10 projects.
Thanks, Chanron
I am having a problem with adding more than 10 projects to the dashboard.
In the Project Details Sheet: I use "insert" command to add more rows, number them (9,10,11,etc.), add the project names as well.
Then I go to the Project Plans Sheet: I copy all of the last Table from Project 10 and Paste that data right next to it skipping two columns as is done in the other sheets.
I then click on the new table (Table 11) and change its name to "Plan11", I also change the formula for the project name from INDEX(lstProjects,10)to INDEX(lstProjects,11)so the table name gets pulled correctly.
When I go back to the Dashboard and look at Project 11 the activity field is blank - like it is not able to pull any info from the Project Plans sheet. Also when I close the file - I get a runtime error '9' - Subscript out of Range message.
Pls help me work this out. I would really like to use this for more than 10 projects.
Thanks, Chanron