Perentage calculation between two dates

asowdi

New Member
Can anyone help me to find the percentage of completion of task? I have task with "start date" and "end date". I want to calculate percentage of completion of task as on today’s date.
 
Hi Ashwin ,


The percentage completion as on date , given a start date and an end date , would be :


100 * (Today's date - Start Date)/(End Date - Start Date)


Narayan
 
Ashwin

The percent complete is (today - start date)/(End date- Start date)
 