How to compute Truck Utilization...

Ysahme


Availability = 1 - Planned Maintenance - Unplanned Maintenance

Utilisation = Availability - Non Production Time


Where everything is a % of Total Time


You may want to have a look at a graphical layout of this in a lot more detail here:

https://www.dropbox.com/s/sntxo5tthxrk9f0/Eqt%20perf.xls


I have removed all the macros, so the buttons don't do anything
 