Hello Excel Experts
have a task list in Excel
task from to days
create account 01.01.2012 01.04.2012 4
setup server 01.01.2012 01.04.2012 91
end user test 01.02.2012 01.03.2012 29
and need a transformation to a month planing with the effort per month like that
month effort
01.2012 23,75
02.2012 114,75
03.2012 23,75
04.2012 23,75
hope someone can help me and guide me to an easy solution
rgds Mike Spass
have a task list in Excel
task from to days
create account 01.01.2012 01.04.2012 4
setup server 01.01.2012 01.04.2012 91
end user test 01.02.2012 01.03.2012 29
and need a transformation to a month planing with the effort per month like that
month effort
01.2012 23,75
02.2012 114,75
03.2012 23,75
04.2012 23,75
hope someone can help me and guide me to an easy solution
rgds Mike Spass