Hello-
I'm trying to use Icon Sets to display % actual complete vs expected % complete for a software build.
The % complete is purely manually entered, however, the expected % complete is calculated based on a formula where the Elapsed Days of Build is Divided by the Total Days of Build. For example, 100 days for total days of build, 50 days have elapsed, the Expected % complete is 50%.
What I'm trying to show is that if the % actual complete is falling behind the expected, then I can show both where it SHOULD be (a green icon), and where it actually IS (yellow or red icon).
If they fall in between the same % brackets, then, there should only be 1 icon of "Green" indicating the project is essentially on track.
I've attached a file for sample...
Thanks!
I'm trying to use Icon Sets to display % actual complete vs expected % complete for a software build.
The % complete is purely manually entered, however, the expected % complete is calculated based on a formula where the Elapsed Days of Build is Divided by the Total Days of Build. For example, 100 days for total days of build, 50 days have elapsed, the Expected % complete is 50%.
What I'm trying to show is that if the % actual complete is falling behind the expected, then I can show both where it SHOULD be (a green icon), and where it actually IS (yellow or red icon).
If they fall in between the same % brackets, then, there should only be 1 icon of "Green" indicating the project is essentially on track.
I've attached a file for sample...
Thanks!