dronka
Member
I'm using the Workday function in a workplan spreadsheet to calculate the due date of tasks given the start date, the number of days required for the task, and holidays. This assumes a 5-day work week.
I'd like to also calculate due dates based on a 6- and 7-day workweek.
I found the Networkdays.Intl function, which I thought addressed this issue. However, unlike the Workday function, you have to enter a begin and an end date. The problem is, I'm trying to solve for the end date given a specific number of days required to do the task.
Can anyone think of how to use this function (or another function) to calculate an end date given start date, number of days required, holidays, and the ability to specify which days are working days and which days are non-working days?
I'd like to also calculate due dates based on a 6- and 7-day workweek.
I found the Networkdays.Intl function, which I thought addressed this issue. However, unlike the Workday function, you have to enter a begin and an end date. The problem is, I'm trying to solve for the end date given a specific number of days required to do the task.
Can anyone think of how to use this function (or another function) to calculate an end date given start date, number of days required, holidays, and the ability to specify which days are working days and which days are non-working days?