My goal is to get the awesome Chandoo project charts to timephase costs or allocate costs accross the "duration" of the task.
E.G Task A starts on column 6 (or a date 3/15) , has a duration of 6 and a cost of $100K, I'd like to fill the the column cells 6...12 for the task row with $100/6 or $16.7.
Task B starts on the next row, on column 10 (or a date again) has a duration of 4 and a cost of $200K, I'd like to fill the column cells 10...14 for Task B's row, with 200/4 or $25K.
Simlar to the way conditional formatting creates a gantt bar, I'd like to allocate or distribute the task funds accross the duration of the task.
sorry for the title, that field froze.
E.G Task A starts on column 6 (or a date 3/15) , has a duration of 6 and a cost of $100K, I'd like to fill the the column cells 6...12 for the task row with $100/6 or $16.7.
Task B starts on the next row, on column 10 (or a date again) has a duration of 4 and a cost of $200K, I'd like to fill the column cells 10...14 for Task B's row, with 200/4 or $25K.
Simlar to the way conditional formatting creates a gantt bar, I'd like to allocate or distribute the task funds accross the duration of the task.
sorry for the title, that field froze.