Hi All,

I have attached spreadsheet with 3 tabs
Details: Please refer employees recruited number for each job per week (Column O to BV)
Summary : This is where the formula should go
Refer: This is reference of a Ramp% value used in formula

There are 10 Jobs for which employees would be recruited within 60 weeks randomly. (Details tab: Column O to BV)
Summary Tab:

1. You can select each job in B1
2. Onboarded employees will be reflected in Row 2 from Column V: Column BL
3. Ramp% will get reflected from Refer tab
4. Production of one employee= Target(always 96)*Ramp%
5. First week employee will do 5%
6. Next week 10%
...likewise
7. Formula should be written in Row#8 of Summary.
8. This should reflect the total production by all employees for the week
9. if that week has 2 employees in Ramp2 week and 3 employees from Ramp3 week, then it should say 10%*96*2 + 15%*96*3
10. I have written the formula which works if all job starts in Week1. But, each job gets its employee in different weeks and ramp% changes for each change


Please help on the formula

Thank you so much
 

Attachments

  • Ramp Up Plan.xlsx
    38.3 KB · Views: 53
Cross post. Please read forum rule and follow it.

 
Thank you for notifying me on the Cross post rules. This would be taken care moving forward. Thanks
 
Hemar5
If You thanked for notifying,
then You also should follow those Rules,
before waiting any replies.
Please, reread those Forum Rules.
 
Back
Top