Dear all, I can't find the right formula or ideas on how to distribute a number into several period based on curve that are set to it, e.g.
I estimate that manhours for a project is 200,000. The project duration should take on 8 months. Thus, if I use Bell Curve, the distribution of the manhours by monthly is:
Months Value
1 9,231
2 19,245
3 31,405
4 40,118
5 40,118
6 31,405
7 19,245
8 9,231
The cumulative of this data will give you a Bell Curve. This function is based on NORMDIST..Is there any example on the Trapezoidal Curve, Front Loaded Curve etc as in most project planning software?
I estimate that manhours for a project is 200,000. The project duration should take on 8 months. Thus, if I use Bell Curve, the distribution of the manhours by monthly is:
Months Value
1 9,231
2 19,245
3 31,405
4 40,118
5 40,118
6 31,405
7 19,245
8 9,231
The cumulative of this data will give you a Bell Curve. This function is based on NORMDIST..Is there any example on the Trapezoidal Curve, Front Loaded Curve etc as in most project planning software?