I love the PM template that creates a two layerred hierarchy for projects via the subtotal command. Could this model be extended to three hierarchical layers.
sorry for the spelling; I need spell check :)
My goal is to get the awesome Chandoo project charts to timephase costs or allocate costs accross the "duration" of the task.
E.G Task A starts on column 6 (or a date 3/15) , has a duration of 6 and a cost of $100K, I'd like to fill the the column cells 6...12 for the task row with $100/6 or...