I am using WORKDAY.INTL to add a Number of days to a Job request to sate the expected Date it will be completed. I was wondering if there was anyway for example if a date is added say after midday that it make the +1 day into the Next day
So if I use =WORKDAY.INTL(D14, 1,1,0)
I want if its Possible
If the date entered in D14 before 12:00 midday it does exactly that put the end Date as The next day
But
If the date entered in D14 after 12:00 midday I want if possible to put the end Date as The day after next
So if I use =WORKDAY.INTL(D14, 1,1,0)
I want if its Possible
If the date entered in D14 before 12:00 midday it does exactly that put the end Date as The next day
But
If the date entered in D14 after 12:00 midday I want if possible to put the end Date as The day after next