I have 32 machines to produce 40,000tons material in 30 days time span
Processing 4 different grades of material say D1,D2,D3,D4 taking 4 processess and all needs to complete
All 4 grades 4 processes are H1,H2,H3,H4 taking following time in hrs(see table)
How to set the grade percentage of material D1…D4 to maximize the production but total grade percentage is equal to 100% and cycle time should not cross more than available hrs
Constraints - Total time should not be more than -32 m/c * 30 days *24hrs =23040 hrs