• Hi All

    Please note that at the Chandoo.org Forums there is Zero Tolerance to Spam

    Post Spam and you Will Be Deleted as a User

    Hui...

  • When starting a new post, to receive a quicker and more targeted answer, Please include a sample file in the initial post.

Reporting Progress and % Complete Using Excel

Chris Jackson

New Member
Hi Everyone,

I have a request to report progress complete against plan using Excel. The attached file shows what I am trying to achieve as the end game but essentially:

1) Each Work Package has a start and finish date
2) The sheet will colour the "%Forecast Bar" if the date in the header (Row 5) is within the start and finish date specified.
3) The % Complete is the % complete of the package as a % of the start and finish dates and will populate the sheet with a value (that I can assign conditional formatting to). This can be rounded up/down.
4) The % Spend is another manually entered value that works identical to the % Complete and populates the sheet with a value in bar form to the progress.

Ideally I need the whole thing to resemble a Gantt but I cannot think of a way to populate the columns based on the % complete.

So I was thinking along the lines of:

61% = fill in as many boxes with a "#" IF the date in Row 5 is less than or equal to 61% of the value of End Date - Start Date.

So if I had a start date of 01/01/18 and an end date of 20/01/18 then 61% would populate the row with a "#" for each date that is less than or equal to 61% of the range between 01/01/18 and 20/01/18 (so that would be 01/01 through to 12/01/2018)

Hopefully that makes sense in conjunction with the sample attached.

If it cannot be done, it cannot be done but it certainly looks feasible, just beyond my range :)

Thanks in advance

Chris
 

Attachments

  • Samples Progress.xlsx
    14.9 KB · Views: 6
Chris Jackson
... or test this too.
If same layout then You could add as many 'Work Packages' as needed.
Press [ReFresh]-button.
The 1st day of Gnatt have to set to cell [D1].
After that all dates, weeks and months would refresh too while [ReFresh].
Blue values should fill manually.
Default Gnatt-colors are right side of [ReFresh]-button.
Those %Progress maybe needs some modifications...
 

Attachments

  • Samples Progress.xlsb
    25 KB · Views: 6
Chris Jackson
... or test this too.
If same layout then You could add as many 'Work Packages' as needed.
Press [ReFresh]-button.
The 1st day of Gnatt have to set to cell [D1].
After that all dates, weeks and months would refresh too while [ReFresh].
Blue values should fill manually.
Default Gnatt-colors are right side of [ReFresh]-button.
Those %Progress maybe needs some modifications...

Thanks vletm, this almost does what I need, the only thing is that it treats the % Spend and the % Complete the same. Is it possible that the button can adjust both of those rows separately?

Great work though. really classy!
 
Chris Jackson
as written Those %Progress maybe needs some modifications...
There were typo with those % - is it better now/Okay?.
... and same time I noticed one more.
Do it all that You need now?
 

Attachments

  • Samples Progress.xlsb
    25.4 KB · Views: 5
That looks great vletm, that really does the trick :)

It's only a minor thing but when you change the dates, the bars should extend the grey to the end date, with the % Forecast shading blue to the % it has achieved, the % Complete to its place and % Spend to its place.

I can see that the % Complete and % Spend shade to the right spot but their Grey does not adjust on refresh and the % Forecast shades all boxes to the end date (and adjusts the Grey). does that make sense at all?

I have to say though, I'm impressed with what it does :)

Regards

Chris
 
Chris Jackson
Test this version ...
There are more checks with those non-black-font-cells.
Some of those would be critical.
You can also select 'the 1st day of chart by selecting any 'gray-day'.
The whole chart will always refresh ( also after change of dates or %Progress ).
If there will be a lot of 'Work Packages' ... I haven't test.
You'll test ...
 

Attachments

  • Samples Progress.xlsb
    34.2 KB · Views: 7
Back
Top