Chris Jackson
New Member
Hi Everyone,
I have a request to report progress complete against plan using Excel. The attached file shows what I am trying to achieve as the end game but essentially:
1) Each Work Package has a start and finish date
2) The sheet will colour the "%Forecast Bar" if the date in the header (Row 5) is within the start and finish date specified.
3) The % Complete is the % complete of the package as a % of the start and finish dates and will populate the sheet with a value (that I can assign conditional formatting to). This can be rounded up/down.
4) The % Spend is another manually entered value that works identical to the % Complete and populates the sheet with a value in bar form to the progress.
Ideally I need the whole thing to resemble a Gantt but I cannot think of a way to populate the columns based on the % complete.
So I was thinking along the lines of:
61% = fill in as many boxes with a "#" IF the date in Row 5 is less than or equal to 61% of the value of End Date - Start Date.
So if I had a start date of 01/01/18 and an end date of 20/01/18 then 61% would populate the row with a "#" for each date that is less than or equal to 61% of the range between 01/01/18 and 20/01/18 (so that would be 01/01 through to 12/01/2018)
Hopefully that makes sense in conjunction with the sample attached.
If it cannot be done, it cannot be done but it certainly looks feasible, just beyond my range![Smile :) :)](data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///yH5BAEAAAAALAAAAAABAAEAAAIBRAA7)
Thanks in advance
Chris
I have a request to report progress complete against plan using Excel. The attached file shows what I am trying to achieve as the end game but essentially:
1) Each Work Package has a start and finish date
2) The sheet will colour the "%Forecast Bar" if the date in the header (Row 5) is within the start and finish date specified.
3) The % Complete is the % complete of the package as a % of the start and finish dates and will populate the sheet with a value (that I can assign conditional formatting to). This can be rounded up/down.
4) The % Spend is another manually entered value that works identical to the % Complete and populates the sheet with a value in bar form to the progress.
Ideally I need the whole thing to resemble a Gantt but I cannot think of a way to populate the columns based on the % complete.
So I was thinking along the lines of:
61% = fill in as many boxes with a "#" IF the date in Row 5 is less than or equal to 61% of the value of End Date - Start Date.
So if I had a start date of 01/01/18 and an end date of 20/01/18 then 61% would populate the row with a "#" for each date that is less than or equal to 61% of the range between 01/01/18 and 20/01/18 (so that would be 01/01 through to 12/01/2018)
Hopefully that makes sense in conjunction with the sample attached.
If it cannot be done, it cannot be done but it certainly looks feasible, just beyond my range
Thanks in advance
Chris