S soul1974 New Member Mar 17, 2024 #1 Hi All, I am trying to create a Gantt chart that automatically updates the percentage completed by calculating the days gone by. The problem I am sitting with is that once it has been completed a day, it increases the percentage. Attachments Project Progress.xlsx 24.6 KB · Views: 7
Hi All, I am trying to create a Gantt chart that automatically updates the percentage completed by calculating the days gone by. The problem I am sitting with is that once it has been completed a day, it increases the percentage.
ETAF Active Member Mar 17, 2024 #2 how about =IF(E9>TODAY(),0,MIN((TODAY()-E9)/(F9-E9),1)) NOT "0" is text and NOT a number so you should use just 0 for a number rather than a calc for 0 - i have just checked to see if the start date is in the future - so E9>today() to make 0 Attachments Project Progress - ETAF.xlsx 24.5 KB · Views: 11
how about =IF(E9>TODAY(),0,MIN((TODAY()-E9)/(F9-E9),1)) NOT "0" is text and NOT a number so you should use just 0 for a number rather than a calc for 0 - i have just checked to see if the start date is in the future - so E9>today() to make 0