Hello,
We always have project reviews on Mondays. In helping our client prepare for these reviews, we have provided them a "checklist":
*T-5 business days (thus, previous Monday): make sure room is reserved
*T-10 business days: (thus, two Mondays before) make sure all people are invited to meeting
*T-15 business days: (thus, three Mondays before) make sure PowerPoint is complete
Etc.
Is there some type of formula in Excel that might work to calculate these T-5, T-10, T-20 dates assuming I have the date of the project review meeting?
Thanks!
Kelly
We always have project reviews on Mondays. In helping our client prepare for these reviews, we have provided them a "checklist":
*T-5 business days (thus, previous Monday): make sure room is reserved
*T-10 business days: (thus, two Mondays before) make sure all people are invited to meeting
*T-15 business days: (thus, three Mondays before) make sure PowerPoint is complete
Etc.
Is there some type of formula in Excel that might work to calculate these T-5, T-10, T-20 dates assuming I have the date of the project review meeting?
Thanks!
Kelly