Creating a Workers Assignment table from Projects assignment list

amitc4u

Member
I have projects that needs workers to be assigned in, by type of the worker.
I would like to assign the workers in the projects ("Projects" sheet) and I want the "Workers" sheet to be filled automatically by the values I entered in the "Projects" sheet.
in the attached file there is an example of how the two tables look like (after it was updated).
Thanks,
Amit
 

Attachments

Maybe something like this? Please see the file attach, using array formulas (when applied you need to press CTRL-SHIFT-ENTER button together) and then copied down and cross as necessary

Regards
 

Attachments

the formulas you provided me work great.
I also need the other way to make the assignment.
meaning, assign the workers in the workers sheet and viewing the results in the Projects table.
please see the attached file (also a request about handaling workers demand).
Thanks a lot,
Amit
 

Attachments

thanks a lot.
I checked it briefly and it seems to be working good.
I'll check it thoroughly and update you with the results.
again, many thanks. this is a great help for me.
Amit
 