Hello,
I posted another question about this chart re: the horizontal axis and scroll bar, but the forum rules say to post other questions separately.
I have chart showing the actual days worked on a project, the days scheduled/predicted to work, and holidays we were not supposed to work during the project.
For the holidays and actual days worked bars overlap, I would either like to include the orange-ish holiday bars inside, like a stacked bar, the actual days worked bars spanning the appropriate dates for the holidays OR just add the holidays as a data label or data call out on the chart and not worry about showing how long the holiday was.
If I do this, then I would prefer to not have the holiday listed on the vertical axis but maybe have it as a label or call out on the graph. The axis is kind of crowded as it is. I had to remove the City A Scheduled, City B Scheduled labels from the axis to show the schedule/predicted dates of the project (the red bars) because it was so crowded on the axis. (The blue bars are the actual days worked on the project.)
This is another thing we have been trying to fix at work and cannot figure it out. We use Excel 2013 and Windows 7 at work.
I posted another question about this chart re: the horizontal axis and scroll bar, but the forum rules say to post other questions separately.
I have chart showing the actual days worked on a project, the days scheduled/predicted to work, and holidays we were not supposed to work during the project.
For the holidays and actual days worked bars overlap, I would either like to include the orange-ish holiday bars inside, like a stacked bar, the actual days worked bars spanning the appropriate dates for the holidays OR just add the holidays as a data label or data call out on the chart and not worry about showing how long the holiday was.
If I do this, then I would prefer to not have the holiday listed on the vertical axis but maybe have it as a label or call out on the graph. The axis is kind of crowded as it is. I had to remove the City A Scheduled, City B Scheduled labels from the axis to show the schedule/predicted dates of the project (the red bars) because it was so crowded on the axis. (The blue bars are the actual days worked on the project.)
This is another thing we have been trying to fix at work and cannot figure it out. We use Excel 2013 and Windows 7 at work.